This question's due date has already passed. You may post a tutorial, but there's no guarantee that the original asker will purchase the tutorial. But other people might!

Question

$23.00 Critical Path Diagram and Calculations Needed

Asked by :
cyberdyne2000
cyberdyne2000
Rating :No Rating
Questions Asked: 8
Tutorials Posted: 0
 
 
Q:

Need an AOA diagram (PERT Chart) based on the scenario below.

  • Outline the critical path and time to completion.
  • Define the number of days to plan for a 95% likelihood of finishing the project within the timeframe.
  • If the project has to be crashed 5 days earlier than the initial critical path, how would this best be accomplished and at what cost.
  • Discuss the various crash options, outlining their benefits and negative aspects.

Time Estimates (days)

Activity  Description         Predecessors    Optimistic    Most Likely    Pessimistic    Crash Cost/Day

A  Funding/liability protection      -                   5                 10                15                $1,000

B  Excavate grounds                  A                 10                 20                40                $2,500

C  Pour foundation                    B                 10                 15                30                $2,000

D Inspect new equipment           B                 10                 20                30                $500

E Install utilities                        C                 15                 20                40                $4,000

F Inspection(utilities)                 E                 0.1                0.1               0.1               $0

G Build out facility                     D,F               15                 20                35                $1,500

H Final inspection                      G                 0.1                0.1               0.1               $0

I Prep for operations-signs, etc.  H                  5                  10                15                $500

J Clean-up                                I                  3                   5                 10                $1,200

 

Available Tutorials to this Question
 
$23.00
critical path
  • This tutorial was purchased 1 time and rated No Rating by students like you.
  • Posted on Mar 31, 2011 at 3:31:52PM
Posted by :
lagvier
lagvier
Rating (54):C+
Questions Asked: 0
Tutorials Posted: 526,
Blog Posts: 1,
Earned: $1,163.82
 
A:
Preview: ... ance = {(pessimistic - optimistic)/6} 2   at 95 ...

The full tutorial is about 34 words long plus attachments.

attachmentlogo

Attachments:
diagram.doc (25K) (Preview)
Book1.xls (22K)