$23.00 Critical Path Diagram and Calculations Needed
- From Mathematics: General-Mathematics , Business: General-Business
- Closed, but you can still post tutorials
- Due on Apr. 03, 2011
- Asked on Mar. 31, 2011 at 07:05:12AM
Need an AOA diagram (PERT Chart) based on the scenario below.
- Outline the critical path and time to completion.
- Define the number of days to plan for a 95% likelihood of finishing the project within the timeframe.
- If the project has to be crashed 5 days earlier than the initial critical path, how would this best be accomplished and at what cost.
- Discuss the various crash options, outlining their benefits and negative aspects.
Time Estimates (days)
Activity Description Predecessors Optimistic Most Likely Pessimistic Crash Cost/Day
A Funding/liability protection - 5 10 15 $1,000
B Excavate grounds A 10 20 40 $2,500
C Pour foundation B 10 15 30 $2,000
D Inspect new equipment B 10 20 30 $500
E Install utilities C 15 20 40 $4,000
F Inspection(utilities) E 0.1 0.1 0.1 $0
G Build out facility D,F 15 20 35 $1,500
H Final inspection G 0.1 0.1 0.1 $0
I Prep for operations-signs, etc. H 5 10 15 $500
J Clean-up I 3 5 10 $1,200